Level 4 Detailed Works Breakdown (2024-2029)
The path from New Basement Excavation to M18 (Feb 2026) is the highest risk area. Any delay in Strut L2 installation directly delays the Transfer Plate.
M30 Milestone is dependent on D01 Marine Deck as-builts and track installation. Structural handovers for DTS begin Dec 2026.
Typical floors for ICON Tower are scheduled on a 10-day cycle, moving to architectural fit-out after L12 structural completion.