RWS P1 MASTER BASELINE SCHEDULE

Level 4 Detailed Works Breakdown (2024-2029)

Commencement 19 AUG 2024
Total Duration 1,645 DAYS
Completion 19 FEB 2029
Piling
ERSS/Excavation
Concrete/Basement
Structure (Towers/MK)
DTS Viaduct
Fit-out/Facade
As-Builts
Detailed Activity / WBS Element
Critical Path Analysis:

The path from New Basement Excavation to M18 (Feb 2026) is the highest risk area. Any delay in Strut L2 installation directly delays the Transfer Plate.

DTS Coordination:

M30 Milestone is dependent on D01 Marine Deck as-builts and track installation. Structural handovers for DTS begin Dec 2026.

Tower Cycle:

Typical floors for ICON Tower are scheduled on a 10-day cycle, moving to architectural fit-out after L12 structural completion.